Norway’s Supreme Court unanimously ruled against the state after finding that its approval process for three oil fields was invalid because it had failed to assess the climate effects of combustion emissions.
The court ordered the approval process to be repeated and required Norway to pay over 5 million kroner in court costs. The companies retain their permits, and production will initially continue unchanged.
The decision concerns Breidablikk, Tyrving and Yggdrasil, fields operated by Norwegian companies Equinor and Aker BP. Norway is western Europe’s leading exporter of gas and oil, while EU project directives require environmental assessment before development and operational plans for oil extraction are approved.
The court found that the state had assessed emissions from the production phase only. It had omitted combustion emissions, which enter the atmosphere when oil is burned.
Under the EU directives, environmental impact assessments must cover combustion emissions from oil extraction before development and operational plans receive approval.
Haldis Tjeldflaat Helle, leader of Greenpeace’s Norwegian section, called the ruling historic.
Greenpeace and Nature and Youth, environmental organisations, brought the case against the Norwegian state over the licensing of the fields. Equinor and Aker BP, which hold the rights to the fields, were not parties to the case.
Two lower court instances had already ruled against the state. The Supreme Court heard the appeal with eleven judges, a panel size used only in cases of special importance.
Breidablikk began production in 2023. Tyrving began production one year later, while Yggdrasil was scheduled to begin production in 2027.
The ruling requires the state to redo the approvals. The companies’ permits remain in force and production is initially unaffected.









Comments (0)